2023 Pavement Management Program

Project Overview

The City of Burien is responsible for repairs and maintenance of approximately 137 centerline miles of paved roads (residential 78%, collector 13%, arterial 9%).

The annual pavement management program consists of pavement preservation applications (crack sealing, micro surfacing and slurry seal coatings), maintenance items (pothole repairs), together with necessary full reconstruction and rehabilitation pavement overlay projects. The purpose of the program is to reduce the overall long-term cost for maintaining the condition of Burien streets.

Each year projects are selected by reviewing the current pavement condition Index (PCI), field inspections, and resident input.

2023 Pavement Repairs and Overlay Projects

The City will be conducing necessary pavement repairs along SW 160th St and S. 160th St., together with pavement preservation and improvements within the Manhattan neighborhood area. The project will consist of pothole repairs, grind and overlay of new asphalt pavement, and ADA-compliant crosswalk improvements along school pedestrian corridors.

2023 Project Areas:

  • Site 1: SW 160th St (from 4th Ave SW to Ambaum Cutoff SW)
  • Site 2: S 160th St (from 5th Place S. to Des Moines Memorial Drive)
  • Site 3: S 192nd  (Manhattan Neighborhood)
  • Site 4: 4th Ave S (Manhattan Neighborhood)

Project Status 

  • April-June 2023: Project Design
  • July-September 2023: Construction

Project Updates

The city will provide updates and notify those residents by mail who may be affected by construction and paving activities.

Project Manager

David Traub, Capital Projects Manager

(206) 241-4647

[email protected]