Project Location
SW 130th St, between 2nd Ave SW and 1st Ave S.

Project Overview
This project will reroute and upsize an existing stormwater force main around private residences between the Hermes Depression and 1st Avenue S. The purpose of this project is to reroute the pumped storm water flow from the Hermes Depression to remain entirely within the right-of-way and avoid being discharged through private property.
Project also includes:
- Replacing pumps and electrical at Hermes Basin.
Project Status
Project Awarded: King Construction Co. Inc, Fife WA
Scheduled Start Date: July 2019
Scheduled Completion Date: Spring 2020
Installation of the new storm water force main pipe, together with site restoration of the road and residential frontages within the right-of-way, along SW 130th St and 1st Ave S., was completed in the fall of 2019.
Replacement of the pumps at Hermes Basin is scheduled for late spring of 2020.
Project Manager
David Traub, (206) 436-5552, davidt@burienwa.gov